Power Plant, Cambridge, MA: Analysis of impact of change orders, permitting, and architectural impacts to schedule for design-build gas-fired cogeneration power plant.

High School, Beacon Falls, CT: Analysis of masonry productivity based on bid rates and actual production. Analysis of impact to other contractors and schedule delays.

VA Hospital, North Chicago, IL: Project Manager for claim involving concrete labor inefficiency, HVAC, sprinkle and electrical coordination, and VA furnished equipment delays. Participated in ADR proceedings
under VABCA.

Desulphurization Ductwork, Tennessee: Analysis of impact of design changes and acceleration to fabrication
and erection of retrofit ductwork (2,000 tons) for power plant.

Ford Ranger Plant, Edison, NJ: Refuted labor inefficiency claims
for plant refitting of paint spray booths and mechanical systems
on an aggressive schedule.

 

 