Power Plant,
Cambridge, MA: Analysis
of impact of change orders, permitting, and architectural impacts to schedule
for design-build gas-fired cogeneration power plant.
University
Athletic Facility, Chapel Hill, NC:
Analysis of workmanship issues, delays and performance of athletic turf and
track systems for indoor athletic facility. Testified as expert in arbitration.
High Rise
Courthouse, Cleveland, OH:
Prepared time impact analysis of stone cladding fabrication and erection delays,
tower crane sequencing and concrete building core construction.
Power Plant,
Londonderry, NH: Evaluation of structural design, piping and electrical
delays to design-build power plant project.
Hotel, Charlotte,
NC: Analysis of delays to
building structure leading up to termination of the general contractor. Testified
as expert in deposition.
Ben Franklin
Elementary School, Philadelphia, PA:
Analysis of schedule delays caused by contaminated soils and structural
steel coordination.
Wastewater Treatment Plant:
Analysis of schedule delays to sand filtration system procurement
and installation for wastewater treatment plant.
Desulphurization System, Taiwan:
Analysis of procurement delays for equipment designed and supplied for FGD
system serving a coal-fired power plant in Taiwan.
Desulphurization System, Turkey:
Analysis of construction and procurement delays for FGD system serving a coal-fired
power plant in Turkey.
Hotel Building, Alpharetta,
GA: Schedule delay analysis and analysis of technical
issues such as A/C unit installation details, differing soil conditions,and
architect's standard of care. Testified as expert in deposition.
Prison Facility, Chester,
PA: Analysis of delays and termination of sitework
& utilities subcontractor and miscellaneous metals subcontractor. Testified
as expert in AAA.
Middle School, Elizabeth,
NJ: Analysis of contractor delays, contractual issues,
structural steel erection and drywall framing. Performed analysis of contractor
costs.
VA Hospital, Boston, MA:
Analysis of constructive acceleration by Owner. Due to no baseline schedule,
delay analysis was based on as-built schedule.
Ras Tanura Oil Refinery,
Saudi Arabia: Extensive analysis of design-build
issues for $115 million contract including preparation of $60 million claim.
Created innovative graphics depicting engineering and construction acceleration
and delays to drawing development. Appeared before Saudi arbitration board.
Faber Elementary School,
Dunellen, NJ: Expert for School Board defense of
differing site conditions and construction delays for new elementary school
construction. Testified in arbitration.
Office High Rise, Boston,
MA: Prepared time impact analyses for design, testing,
fabrication and erection of granite cladding system for 75 State Street building.
Extensive analysis of subcontractor costs and labor inefficiency.
Downstate Prison, Fishkill,
NY: Analyzed foundation delays and additional costs
arising from differing site conditions and winter concrete and masonry labor
inefficiency.
Psychiatric Hospital, New
York: Evaluated HVAC, radiant heat piping and RF
Shielded room coordination and acceleration issues.
Sheraton Hotel, Stamford,
CT: Analyzed foundation and steel erection delays
and finishes changes by the Owner. Used models to demonstrate complex construction
sequencing.
Peabody Hotel, Orlando, FL:
Schedule and technical evaluation for Gilbane involving fast-track design
delays and impact of curtainwall subcontractor bankruptcy.
Metropolitan Plaza, Atlantic
City, NJ: Prepared contractor claim involving precast
shop drawing delays, code compliance issues and water infiltration problems
with EIFS cladding.
Showboat Casino,
Atlantic City, NJ: Prepared drywall subcontractor claim to recover
costs from extensive acceleration and change order impacts.
Social Security
Building, New York City, NY: Extensive CPM time impact analysis
involving delays to shoring and sheeting, foundations, structural steel,
exterior masonry, windows, mechanical and electrical work. Evaluated impact
of extensive changes and acceleration. Informal testimony given at mini-trial
proceedings.
King Khalid
Military City, Saudi Arabia: Schedule analysis of design, fabrication
and erection of barracks utilizing over 25,000 precast concrete elements on
a $1 billion project.